Click on thumbnail to see Full Size Image.

   

Items 1 thru 25 of 110

Steel beam installation at the Front-end building (building 8100) - Spallation Neutron Source (SNS) construction site, November 6, 2001.

08172-2001

Steel beam installation at the Front-end building (building 8100) - Spallation Neutron Source (SNS) construction site, November 6, 2001.

08170-2001

Interior construction view of the Linac Tunnel (building 8200) - Spallation Neutron Source (SNS) construction site, November 6, 2001.

08169-2001

Concrete pour at the Target Building No. 1 (building 8700) - Spallation Neutron Source (SNS) construction site, November 5, 2001.

08160-2001

Concrete pour at the Target Building No. 1 (building 8700) - Spallation Neutron Source (SNS) construction site, November 5, 2001.

08159-2001

Concrete pour at the Target Building No. 1 (building 8700) - Spallation Neutron Source (SNS) construction site, November 5, 2001.

08158-2001

Water tower base - Spallation Neutron Source (SNS) construction site, November 5, 2001.

08151-2001

Water tower base - Spallation Neutron Source (SNS) construction site, November 5, 2001.

08150-2001

GPS monument on hill next to the water tower - Spallation Neutron Source (SNS) construction site, November 5, 2001.

08146-2001

GPS monument on hill next to the water tower - Spallation Neutron Source (SNS) construction site, November 5, 2001.

08145-2001

GPS monument on hill next to the water tower - Spallation Neutron Source (SNS) construction site, November 5, 2001.

08144-2001

Fixed position 4-5 - from the hill looking toward the future location for the Sub-station (building 8914) - Spallation Neutron Source (SNS) construction site, November 5, 2001.

08143-2001

Water tower base. Spallation Neutron Source (SNS) construction site, November 27, 2001.

08602-2001

Concrete and rebar inside the Target building (building 8700). Spallation Neutron Source (SNS) construction site, November 27, 2001.

08600-2001

Crane, concrete and rebar inside the Target building (building 8700). Spallation Neutron Source (SNS) construction site, November 27, 2001.

08599-2001

Concrete and steel rebar of the Target building (building 8700). Spallation Neutron Source (SNS) construction site, November 27, 2001.

08598-2001

Fixed position 4-5 - from the hill looking toward the future site of the Sub-station (building 8914). Spallation Neutron Source (SNS) construction site, November 27, 2001.

08597-2001

Construction on north side of the Linac Tunnel (building 8200) and Front-end building (building 8100). Spallation Neutron Source (SNS) construction site, November 27, 2001.

08596-2001

Construction on north side of the Linac Tunnel (building 8200) and 8201. Spallation Neutron Source (SNS) construction site, November 27, 2001.

08595-2001

Underground pipe installation at the Spallation Neutron Source (SNS) construction site, November 27, 2001.

08590-2001

Underground pipe installation at the Spallation Neutron Source (SNS) construction site, November 27, 2001.

08589-2001

Underground pipe installation at the Spallation Neutron Source (SNS) construction site, November 27, 2001.

08588-2001

Concrete pour and rebar installation at the Target Building No. 1 (building 8700) - Spallation Neutron Souce (SNS) construction site, November 8, 2001.

08244-2001

Installation of the Water tower base - Spallation Neutron Souce (SNS) construction site, November 8, 2001.

08243-2001

Concrete pour in the Target Building No. 1 (building 8700) - Spallation Neutron Souce (SNS) construction site, November 8, 2001.

08242-2001

Water tower base - Spallation Neutron Source (SNS) construction site, November 5, 2001.

08137-2001