South entrance road construction looking northwest, east end of the construction site. Aerial of the Spallation Neutron Source (SNS) construction site and surrounding area, August 22, 2000.
05677-2000
|
|
Steel beam installation at the Front-end building (building 8100) - Spallation Neutron Source (SNS) construction site, November 6, 2001.
08172-2001
|
|
Steel beam installation at the Front-end building (building 8100) - Spallation Neutron Source (SNS) construction site, November 6, 2001.
08170-2001
|
|
Interior construction view of the Linac Tunnel (building 8200) - Spallation Neutron Source (SNS) construction site, November 6, 2001.
08169-2001
|
|
Concrete pour at the Target Building No. 1 (building 8700) - Spallation Neutron Source (SNS) construction site, November 5, 2001.
08160-2001
|
|
Concrete pour at the Target Building No. 1 (building 8700) - Spallation Neutron Source (SNS) construction site, November 5, 2001.
08159-2001
|
|
Concrete pour at the Target Building No. 1 (building 8700) - Spallation Neutron Source (SNS) construction site, November 5, 2001.
08158-2001
|
|
Water tower base - Spallation Neutron Source (SNS) construction site, November 5, 2001.
08151-2001
|
|
Water tower base - Spallation Neutron Source (SNS) construction site, November 5, 2001.
08150-2001
|
|
GPS monument on hill next to the water tower - Spallation Neutron Source (SNS) construction site, November 5, 2001.
08146-2001
|
|
GPS monument on hill next to the water tower - Spallation Neutron Source (SNS) construction site, November 5, 2001.
08145-2001
|
|
GPS monument on hill next to the water tower - Spallation Neutron Source (SNS) construction site, November 5, 2001.
08144-2001
|
|
Fixed position 4-5 - from the hill looking toward the future location for the Sub-station (building 8914) - Spallation Neutron Source (SNS) construction site, November 5, 2001.
08143-2001
|
|
Water tower base. Spallation Neutron Source (SNS) construction site, November 27, 2001.
08602-2001
|
|
Concrete and rebar inside the Target building (building 8700). Spallation Neutron Source (SNS) construction site, November 27, 2001.
08600-2001
|
|
Crane, concrete and rebar inside the Target building (building 8700). Spallation Neutron Source (SNS) construction site, November 27, 2001.
08599-2001
|
|
Concrete and steel rebar of the Target building (building 8700). Spallation Neutron Source (SNS) construction site, November 27, 2001.
08598-2001
|
|
Fixed position 4-5 - from the hill looking toward the future site of the Sub-station (building 8914). Spallation Neutron Source (SNS) construction site, November 27, 2001.
08597-2001
|
|
Construction on north side of the Linac Tunnel (building 8200) and Front-end building (building 8100). Spallation Neutron Source (SNS) construction site, November 27, 2001.
08596-2001
|
|
Construction on north side of the Linac Tunnel (building 8200) and 8201. Spallation Neutron Source (SNS) construction site, November 27, 2001.
08595-2001
|
|
Underground pipe installation at the Spallation Neutron Source (SNS) construction site, November 27, 2001.
08590-2001
|
|
GPS monument on hill next to the water tower - Spallation Neutron Source (SNS) construction site, November 5, 2001.
08149-2001
|
|
Footer for the Target Building No. 1 (building 8700) - Spallation Neutron Source (SNS) construction site, November 6, 2001.
08175-2001
|
|
Rebar in the floor of the Target Building No. 1 (building 8700) - Spallation Neutron Souce (SNS) construction site, November 8, 2001.
08251-2001
|
|
Rebar in the floor of the Target Building No. 1 (building 8700) - Spallation Neutron Souce (SNS) construction site, November 8, 2001.
08250-2001
|
|
Rebar in the floor of the Target Building No. 1 (building 8700) - Spallation Neutron Souce (SNS) construction site, November 8, 2001.
08249-2001
|