Click on thumbnail to see Full Size Image.

   

Items 1 thru 25 of 988

Fixed position 2 - Front-end building (building 8100), southwest of the Linac Tunnel (building 8200). Spallation Neutron Source (SNS) construction site, November 28, 2001.

08608-2001

Construction of the exit 8201 from the Linac Tunnel (building 8200). Spallation Neutron Source (SNS) construction site, November 28, 2001.

08607-2001

Interior construction view of the Linac Tunnel (building 8200) - Spallation Neutron Source (SNS) construction site, November 6, 2001.

08169-2001

Construction on north side of the Linac Tunnel (building 8200) and 8201. Spallation Neutron Source (SNS) construction site, November 27, 2001.

08595-2001

Fixed position 2 - Front-end building (building 8100), southwest of the Linac Tunnel (building 8200). Spallation Neutron Source (SNS) construction site, November 27, 2001.

08592-2001

Fixed position 2 - Front-end building (building 8100), southwest of the Linac Tunnel (building 8200). Spallation Neutron Source (SNS) construction site, November 5, 2001.

08138-2001

Concrete pour and installation of the Linac Tunnel (building8200). Spallation Neutron Source (SNS) construction site, November 28, 2001.

08609-2001

Construction on north side of the Linac Tunnel (building 8200) and 8201. Spallation Neutron Source (SNS) construction site, November 27, 2001.

08594-2001

Fixed position 2 - Front-end building (building 8100), southwest of the Linac Tunnel (building 8200). Spallation Neutron Source (SNS) construction site, November 27, 2001.

08593-2001

Construction on north side of the Linac Tunnel (building 8200) and Front-end building (building 8100). Spallation Neutron Source (SNS) construction site, November 27, 2001.

08596-2001

Interior intersection of the Linac Tunnel (building 8200) and Ring Tunnel (building 8420). Spallation Neutron Source (SNS) construction site, January 14, 2004.

00213-2004

Equipment on interior of the Linac Tunnel (building 8200). Spallation Neutron Source (SNS) construction, November 4, 2004.

08199-2004

Fixed position 4-7 - from the hill looking toward the west end of the Linac Tunnel (building 8200). Spallation Neutron Source (SNS) construction site, October 5, 2004.

07068-2004

Fixed position 2 - Front-end building (building 8100), southwest of the Linac Tunnel (building 8200). Spallation Neutron Source (SNS) construction site, October 5, 2004.

07053-2004

Fixed position 2 - Front-end building (building 8100), southwest of the Linac Tunnel (building 8200). Spallation Neutron Source (SNS) construction site, October 5, 2004.

07052-2004

Fixed position 4-7 - from the hill looking toward the west end of the Linac Tunnel (building 8200). Spallation Neutron Source (SNS) construction site, October 5, 2004.

07069-2004

Fixed position 4-7 - from the hill looking toward the west end of the Linac Tunnel (building 8200). Spallation Neutron Source (SNS) construction site, October 5, 2004.

07054-2004

Fixed position 4-7 - from the hill looking toward the west end of the Linac Tunnel (building 8200). Spallation Neutron Source (SNS) construction site, October 5, 2004.

07055-2004

Fixed position 4-7 - from the hill looking toward the west end of the Linac Tunnel (building 8200). Spallation Neutron Source (SNS) construction site, April 24, 2004.

02788-2004

Fixed position 2 - Front-end building (building 8100), southwest of the Linac Tunnel (building 8200). Spallation Neutron Source (SNS) construction site, April 24, 2004.

02780-2004

Fixed position 3 - north of the Linac Tunnel (building 8200). Spallation Neutron Source (SNS) construction site, April 24, 2004.

02781-2004

Fixed position 4-4 - from the hill looking toward the Support Buildings (building 8910) and Linac Tunnel (building 8200). Spallation Neutron Source (SNS) construction site, April 24, 2004.

02786-2004

Interior of the Linac Tunnel (building 8200). Spallation Neutron Source (SNS) construction, May 20, 2004.

03058-2004

Interior connection at the Ring Tunnel (building 8420) and Linac Tunnel (building 8200). Spallation Neutron Source (SNS) construction, May 20, 2004.

03059-2004

Fixed position 2 - Front-end building (building 8100), southwest of the Linac Tunnel (building 8200). Spallation Neutron Source (SNS) construction site, April 24, 2004.

02418-2004

Fixed position 2 - Front-end building (building 8100), southwest of the Linac Tunnel (building 8200). Spallation Neutron Source (SNS) construction site, April 14, 2004.

02385-2004